Appendix B Installing the Slide Assembly in the Rack
Verifying the Rack Requirements
98 ATL P1000 Series User’s Guide
Verifying the Rack Requirements
B
Before installing the slide assembly in the rack, verify that the rack
meets the following requirements.
Rack Current Rating
Consideration
B
Consider the current rating of the rack before installing more than one
P1000 library. The P1000 library is rated 6A/3A (120V/230V). This
means that no more than two libraries can be installed in a typical
15A/120V rack.
If other equipment is installed in the rack, determine the total current
rating of all the equipment before adding the P1000 library to the rack.
Grounding
B
The P1000 must be connected to a grounded power outlet. If the
library is rack-mounted, the rack must also be grounded.
Temperature
B
The rack temperature should be less than 32
°
C.